Indonesia plans 14,000 km of new and reactivated railway tracks, Vientiane–Vung Ang Railway, East Coast Rail Link (Malaysia) is set to open on December 12, North-South Commuter Railway (Philippines) will be partially open by the end of 2027, Bangkok–Nong Khai High-Speed Railway update, Hanoi–Quang Ninh High-Speed Railway begins construction.
This is the 2026 Future Southeast Asia report for railways in Southeast Asia.
I keep track of every railway project planned and under construction in Southeast Asia, and this report is a summary of major news updates over the last 12 months.
This report doesn’t cover urban rail transit, which is covered in a separate annual report.
News
🇰🇭 Cambodia
Cambodia has grand plans for new and improved railways, but there have been no meaningful updates over the last 12 months. Prime Minister Hun Manet mentioned the construction of the new Poipet-Siem Reap-Phnom Penh railway at an event, and there have been talks with China and Japan regarding railway development.
🇮🇩 Indonesia
Indonesia currently operates 7,000 kilometres of active railway tracks, and it is planning for 14,000 km of new and reactivated railway tracks by 2045. Most of the active railways in Indonesia are in Java, so this includes building railways in Sumatra, Kalimantan, and Sulawesi.
Jakarta – Bandung High-Speed Railway (Whoosh)
The Jakarta-Bandung High-Speed Railway (Whoosh) celebrated its third anniversary in October, but the year has been overshadowed by what to do with the mounting debt. The plan is to transfer Whoosh shares to the Finance Ministry, which will be confirmed by December.
Jakarta – Surabaya High-Speed Railway
The Whoosh Debt problem has complicated the plan to extend the line to Surabaya. A plan was announced to form a committee regarding the extension in January.
Sumatra
There was another announcement about developing the Trans-Sumatra Railway from Aceh to Lampung. The Trans-Sumatra Railway was supposed to begin construction in 2015, so these near-annual updates are meaningless without a specific timeline.
One specific plan announced was the railway reactivation project in West Sumatra (archive). This is for a 15.3-km section of the old coal railway connecting Kayu Tanam and Padang Panjang near Padang. This is not on the proposed north-south route from Aceh to Lampung, but it’s a good plan for West Sumatra.

Kalimantan
Indonesia is in talks with China and Russia regarding Kalimantan railways, though no routes are mentioned in the articles. Any railway in Kalimantan would most likely be a mining railway with passenger trains as an afterthought (like the coal railways in South Sumatra).
Sulawesi
Indonesia invited Russian firms to join rail projects, including the Trans-Sulawesi Railway. As with Sumatra and Kalimantan, the announcements were light on details.
Any new railway would have to be a continuation of the current short line that starts in Makassar. I visited this line in 2024, and here is my review of the Makassar-Pare Pare Railway.
🇱🇦 Laos
Laos-China Railway
The Laos-China Railway has recorded over 840,000 cross-border travellers, and cross-border freight has exceeded 20 million tonnes since the line opened in December 2021.
Vientiane-Vung Ang Railway
The Vientiane – Vung Ang Railway is the proposed railway that will provide Laos with direct access to the closest seaport in Vietnam.
According to local media, the 452 km Laos section from Vientiane to the Vietnamese border is scheduled to begin construction this year. The railway is expected to cost about US$6.6 billion and be operational by 2030.
The line is being built by PTL Holding Company Limited (Petroleum Trading Lao Public Company), and one of the selling points of the railway is to secure fuel shipments to landlocked Laos.
Work is currently underway to clear the rail corridor of unexploded ordnance (UXO).
Vientiane – Champasak Railway
With the Vientiane – Vung Ang Railway closer to becoming a reality, there has also been talk of then extending the line from Thakhek to Pakse and Cambodia.
Here is the factsheet for the Vientiane – Champasak Railway.
🇲🇾 Malaysia
East Coast Rail Link
The East Coast Rail Link (ECRL) is the longest new railway under construction on this roundup, and it is set to open on December 12, 2026.

The ECRL will travel from Gombak (the station closest to KL) to Kota Bharu, and it will have a top speed of 160 km/h (semi-high-speed), which is ideal for a railway of this length.
Gombak Station is at the northern end of the Kelana Jaya Line, so it will be possible to get the LRT from the KL old town area to the ECRL station.
Gemas-Johor Bahru Electrified Double Track (EDT) project
After years of delays, the Gemas – JB Electric Double-Track Project was completed in December 2025. This means that it’s now possible to travel from Kuala Lumpur to Johor Bahru in 4 hours on one train. The previous journey involved an electric train from KL to Gemas, and then switching to a diesel train from Gemas to JB.
Selangor Rail Line
The Selangor Rail Line is still being studied, with the first phase of the project’s development expected to take 10 years. The Selangor Line would connect with the ECRL and run along the West Coast of Peninsular Malaysia.
Trans-Borneo Railway
A Federal study has found that the Trans-Borneo Railway project is feasible “between major population centres, industrial areas, ports, airports and logistics nodes across Sarawak, Sabah, Brunei and Kalimantan, Indonesia.”
🇲🇲 Myanmar
Muse-Mandalay-Kyaukphyu Railway
China is still pushing for the railway from Muse to Kyaukphyu. China is currently building the Dali–Ruili railway, which would connect to the Muse-Kyaukphyu rail, thus giving China access to the Bay of Bengal.
🇵🇭 Philippines
North–South Commuter Railway
The North-South Commuter Railway (NSCR) is a commuter railway serving Greater Manila. Last year’s report stated that the line would be partially opened in 2026, but now it is expected that the line will be partially open from Malanday, Valenzuela, to Malolos, Bulacan by the end of 2027.
PNR South Long Haul
The PNR South Long Haul (PNR Bicol) is a project to reconstruct the 565 km railway in Southern Luzon. The project was derailed in 2025 after funding from China was ruled out due to territorial disputes in the West Philippine Sea. The Philippines has considered Japan, the US, and India as alternative financiers.
I rode the remnants of the Philippines South Main Line this year, and the line is in such bad shape that it would require a complete rebuild.
Mindanao Railway
The Mindanao Railway project continues to go nowhere. The government is still looking to secure funding after the China option fell through, with Japan and India being courted as alternatives.
🇸🇬 Singapore
Now that the KL-JB route operates as a single line, pundits are now asking what is next for the high-speed rail to Singapore? The 4.5-hour trip doesn’t include the border crossing and then another hour of travel by metro to central Singapore.
Another article makes the case for reserving land for the railway alongside the Southern West Coast Expressway (WCE).
🇹🇭 Thailand
Bangkok – Nong Khai High-Speed Railway (Thai-China Railway)
The Bangkok–Nong Khai High-Speed Railway is still beset with delays. It was announced at the start of the year that the Bangkok–Nakhon Ratchasima section would be delayed by a year (to 2030), and this was before the crane collapse that killed 30 people. The latest target is to open in 2031.
The Ayutthaya High-Speed Railway Station is set to proceed with construction in 2027 after being delayed due to concerns about city heritage.
Meanwhile, the Nakhon Ratchasima–Nong Khai section (which has not begun construction yet) is expected to be ready by 2033.
The proposed Mekong River Railway Bridge that will allow the high-speed railway to cross into Laos is still being discussed.
Don Mueang–Suvarnabhumi–U-Tapao high-speed railway
The 3-airport high-speed railway is on the precipice of collapse after the CP Group-led private consortium asked to terminate its contract. The PM insists that the high-speed rail contract must be fulfilled, but the government is also considering a reduced-speed option of 160 km/h, compared with the current plan of 250 km/h.
Double-tracking project
Thailand’s Cabinet has approved the construction of three southern double-track railway lines:
– Chumphon-Surat Thani, 168 km
– Surat Thani-Hat Yai-Songkhla, 321 km
– Hat Yai-Padang Besar, 45 km
The government is also reviewing other double-tracking projects:
– Pak Nam Pho – Den Chai
– Thanon Chira Junction – Ubon Ratchathani
Den Chai – Chiang Rai – Chiang Khong Railway
The Den Chai – Chiang Rai – Chiang Khong Railway is progressing well, with Thailand’s longest rail tunnel nearing completion and an expected opening date of 2028 (unchanged from last year’s update).
Ban Phai – Mukdahan – Nakhon Phanom Railway
Like the Chiang Rai Railway project, the Ban Phai – Mukdahan – Nakhon Phanom Railway is a quiet achiever of the railway projects in Thailand. This line is expected to open in 2029. This line will bring new tourism opportunities to that part of the Isaan region, and it could also change the fortunes of Thakhek in Laos.
I am looking forward to being able to get a train to Chiang Rai and Nakhon Phanom, but it will forever be a disappointment that Thailand elected to build a metre-gauge railway instead of modernising the railway network with a standard-gauge electric railway. I wrote about Thailand’s mediocre master plan for rail development.
Chumphon – Ranong Railway
The Chumphon – Ranong Railway is being reconsidered now that the Thai Land Bridge project has been put on hold (which was always a terrible idea).
Thap Put – Krabi Railway
The Thap Put – Krabi Railway will branch off the proposed Surat Thani – Phuket line at Thap Put and connect Krabi and Krabi Airport. Construction is expected to begin in 2034.
🇻🇳 Vietnam
North-South High-Speed Railway
Planning for the North-South High-Speed Railway project is continuing, but the goalposts have moved again. Last year, the government moved the start of construction from 2027 to December 2026, but now it has been moved back to the end of 2027. The completion date is still set for 2035.
The rail technology provider has not been announced, but the government has been shopping around. If they have picked a country to partner with, they have not made it publicly known.
One consortium has bid for the North-South high-speed railway feasibility study.
One of the potential causes of construction delays will be land clearance, so the cities and provinces that the railway will pass through are already clearing a pathway. Quang Tri, Hue, and Da Nang (among others) have already begun building resettlement areas for residents who are being moved.
Lao Cai-Hanoi-Hai Phong Railway
The Lao Cai-Hanoi-Hai Phong Railway broke ground on December 19 2025. This was for five of the stations and not the actual railway. The groundbreaking was part of a mass ceremony of 234 key projects that took place on that auspicious day in Vietnam.
As with the North-South project, most of this year has been focused on land clearance before construction begins in earnest.
Hanoi – Dong Dang Railway
The Hanoi – Dong Dang Railway is the current line that connects Hanoi to Nanning in China. The plan is to upgrade the railway to a double-tracked standard-gauge railway with a design speed of 160 km/h.
The current line is a single-track, dual-gauge railway, with trains from China using the standard-gauge section of the dual gauge. I took the train from Hanoi to Nanning this year, and while it was a good experience, it is too slow considering how close the cities are.
Personally, I would have preferred if a high-speed rail were built on this section. China has built a separate high-speed line from Nanning to the Vietnam border (with a top speed of 250 km/h), so it would have been good if the same train ran through the border to Hanoi. On the other hand, everyone has to get off the train with their luggage at the border, so it won’t matter too much if it is a different train (as long as the trains are at the same station).
Hai Phong–Ha Long–Mong Cai Railway
The Hai Phong–Ha Long–Mong Cai Railway is the third line that will connect Northern Vietnam with China. This will connect with the Dongxing – Fangchenggang line in China.
Detailed plans for the railway are expected to be completed in 2026.
Hanoi–Quang Ninh High-Speed Railway
One of the most surprising railway projects in Southeast Asia is the Hanoi–Quang Ninh High-Speed Railway. The line was first proposed in December 2024, and construction for the line broke ground in April 2026. By comparison, the North-South HSR was first proposed in 2005, and they are still planning it.
The Hanoi–Quang Ninh high-speed line will be approximately 120 km in length and have a top speed of 350 km/h, with an investment of US$5.4 billion. The railway is being built in partnership with Siemens Mobility.

This is a private railway that is not part of the national master plan. It is being built by Vinspeed, which is the railway subsidiary of Vingroup. In addition to getting tourists to Ha Long Bay quickly, it is mainly being built to serve the mega urban area project being built by Vingroup in Quang Ninh.
Vinspeed is also building a high-speed railway in Ho Chi Minh City (Ben Thanh-Can Gio). This is technically part of the metro system, so I will feature this in the separate annual urban rail transit report.
Ho Chi Minh City – Can Tho Railway
The HCMC-Can Tho Railway has been in planning for years, but the latest report says that it will begin construction in 2028. This will be a standard-gauge railway with a top speed of 160 km/h.
There are plans for 28 transit-oriented urban areas along the railway, and in a stroke of good planning, the planned Can Tho 2 Bridge will be a road/rail bridge.
Here is a video that depicts the route from An Binh Station to Can Tho Station.
Da Lat–Thap Cham Railway restoration
The Da Lat–Thap Cham railway restoration is still being considered among a list of projects calling for foreign direct investment (FDI) during the 2026–2030 period.
Bien Hoa – Vung Tau Railway
The Bien Hoa-Vung Tau Railway is proposed with a speed of 160km/h. 132-kilometre railway is planned to begin construction before 2030. This line was first announced in 2013, so it is absurd that it is taking so long to plan, when the Ha Long high-speed railway began construction within 2 years of being announced.
Vientiane – Vung Ang Railway
While Laos is expected to start construction at their end in 2026, Vietnam is expected to begin construction of the Vietnam section in 2027.
Further reading
I publish a monthly newsletter related to Southeast Asia news. This newsletter covers new lines, route updates, and trip reports, so there are links not covered by Future Southeast Asia. Subscribe here.
I’m also the admin of the Southeast Asia Railways Facebook Group, so join that group for regular news updates.